The safety and stability of water-stop curtains have significant impacts on surrounding environments. During actual construction, failures may occur due to various factors such as design flaws, inadequate geological surveys, or poor quality control, leading to project delays or safety incidents. Therefore, studying the causes of water-stop curtain failure and effective treatment methods is crucial.
A deep excavation refers to digging projects with a depth of 5 meters or more, or those involving three or more basement levels. In cases where geological conditions or surrounding environments are complex, even shallower excavations may be classified as deep.
According to regulations in China:
Excavations exceeding 5 meters (including 5 meters) in depth require specialized plans for earthwork, support, and dewatering.
Excavations under 5 meters but with complex geological conditions, nearby structures, or underground pipelines also need strict safety assessments.
Due to high-risk factors, deep excavation projects require safety evaluations involving experts, project managers, supervisors, safety officers, and technical personnel from construction, survey, and design teams.
A water-stop curtain is a critical component in excavation projects, designed to prevent or reduce groundwater seepage, ensuring construction safety and preventing post-construction settlement.
It consists of three main parts:
Retaining Piles – Similar to retaining walls, typically made of reinforced concrete piles with gaps between them.
Water-Sealing Layer – Reinforces soil and blocks water flow between inside and outside the excavation, often using cement mixing piles or compaction grouting.
Support Structure – Provides additional reinforcement, especially in large or ultra-deep excavations where diaphragm walls may be used.
Water-stop curtain failure can result from multiple factors, which must be analyzed based on excavation conditions and pile quality. Leakage types can be categorized as:
By Depth: Above or below the excavation level.
By Material: Reinforced concrete cracks or cement-soil gaps.
Improper Cold Joint Treatment – Poor sealing at construction joints leads to localized leaks.
Low-Quality Mixing Piles – Rapid dewatering or excessive water extraction dilutes the unset cement slurry, weakening pile integrity.
Premature Excavation – Immediate large-scale digging after curtain installation causes structural displacement and damage.
If the water-stop curtain does not fully seal the aquifer, excavation reduces soil pressure, leading to piping or sand boiling near weak points (e.g., wells, tool piles, or retaining piles). This may cause base heave, endangering nearby structures and pipelines.
Leaking underground pipes
Proximity to rivers
Excessive rainfall saturates the oil
These increase active earth pressure, causing deformation and cracks in the curtain, potentially leading to major accidents.
Despite initial surveys indicating no high-pressure aquifer, leaks may occur due to:
Pipe leakage
High soil moisture
Poor-quality cement mixing piles
Initial leaks may carry sediment, while later-stage leaks appear clear, indicating minor underground voids.
Poor-quality deep mixing walls (insufficient overlap, weak joints, or uneven mixing)
Soil reactivity affecting cement solidification
These lead to minor but sediment-rich leaks, potentially forming sinkholes if untreated.
Install grouting holes in two rows (0.5m apart, staggered pattern).
First-row holes are grouted vertically (6–8m depth).
Use a 1:1 cement-sodium silicate mix at 1 MPa pressure.
Install relief wells (10–12m deep, 20m spacing) to reduce the water head difference.
Use intermittent pumping to minimize seepage.
Install steel mesh (8mm bars, 15cm spacing) on pile gaps.
Apply 6cm of C20 shotcrete in two layers (3cm each).
Pour dense concrete at the base (6.8–7m depth) to block seepage.
Inject grout (6m depth, 0.5 MPa pressure) near affected buildings.
Monitor ground movement; stop if uplift occurs.
External grouting (first row, then second row).
Internal shotcrete application.
Leak sealing with cement bags if detected.
Concrete barrier at pile-base junctions.
Water Level Monitoring: Observe external water levels via boreholes. Stable readings indicate successful treatment.
Settlement Monitoring: Install sensors (4 per building). Acceptable settlement: <2 cm.
Strict Quality Control – Regular inspections and timely repairs ensure curtain effectiveness.
Controlled Dewatering – Begin only after the curtain gains sufficient strength.
Site-Specific Solutions – Analyze causes before applying treatments.
Proper design, construction, and maintenance of water-stop curtains are essential for deep excavation safety. By understanding failure causes and implementing effective treatments, risks can be minimized, ensuring project success and structural integrity.
Bored cast-in-place piles have the advantages of low construction noise, and low vibration, pile length…
Bored cast-in-place piles have the advantages of low construction noise, and low vibration,…
The four major construction technologies are dry hole forming technology, slurry static pressure technology, casing…
Soil nail support is a new type of retaining structure developed in recent years for…
Pile Foundation Classification and Construction Principles 1. Classification According to Load-Bearing Piles ① Friction type…
Steel sheet pile cofferdams are suitable for basic projects such as sandy soil, gravel soil,…