Blog

Pile Construction Guidelines: Best Practices for Prestressed Concrete Piles

1. Basic Regulations

  • Dense Pile Groups: Construction should proceed from the center outward symmetrically.
  • Pile Groups Adjacent to Buildings: Construction should move from the building side to the opposite side.
  • Based on Foundation Design Elevation: Deeper piles should be constructed before shallower ones.
  • Based on Pile Specifications (Diameter & Length): Larger-diameter and longer piles should be constructed first.
  • Prestressed Concrete Pile Connections:
    • Methods: End-plate welding, flange connection, mechanical interlocking, threaded connection.
    • Maximum of 3 joints per pile.
  • Pile Ends in Water-Sensitive Strata:
    • If embedded in easily softened weathered rock or unsaturated soil, apply anti-seepage measures (e.g., micro-expansion concrete fill or flexible waterproof coating) within 2m of the pile tip.
  • Test Piling:
    • Conduct trial piles before official construction (1% of total piles, minimum 5).

2. Test Piling Requirements

Basic Guidelines:

  • Use actual pile locations for test piles (later used as working piles).
  • Test piles should represent site geology, size, and length.
  • Place near key boreholes.
  • Follow the same construction method as production piles.
  • Use high-strain dynamic testing (PDA) during trial driving.

High-Strain Testing Procedure:

  1. Estimate pile length based on geotechnical data + 3–4m.
  2. Drive pile using standard methods, recording details.
  3. Pause near bearing layer; install sensors and resume hammering.
  4. Stop when resistance reaches 2Ra/a (where Ra = design capacity, a = soil recovery factor: 1.2–1.4 for clay, 0.9–1.1 for sand).
  5. Measure depth, final penetration, and blows per last meter.
  6. Re-test after 24h. If resistance ≥ 2Ra, adopt the results; otherwise, adjust a and repeat.

Required Test Data:

  • Ultimate vertical bearing capacity.
  • Side friction and end resistance.
  • Maximum hammer energy & pile stresses.
  • Pile integrity.
  • Embedment depth, blow counts, and penetration rate.

3. Construction Process Flow

  1. Survey & Layout
  2. Pile Rig Setup
  3. Pile Alignment
  4. Driving
  5. Splicing (if needed)
  6. Final Driving (Termination Criteria)
  7. Cutting Excess Pile Length
  8. Inspection & Testing

4. Operational Methods

Survey & Layout

  • Control points should avoid pile interference.
  • Mark pile positions with stakes/lime.

Pile Rig Setup

  • Ensure “three accessibilities” (water, power, road) and level ground (bearing capacity ≥140 kPa/m²).
  • Soft Ground Improvement:
    • Fill with 0.5–1m brick slag for soft clay.
    • 0.3–0.5m brick slag for loose fill.
  • Adjust rig for vertical alignment (±0.5% tolerance).

Pile Handling

  • Precast piles must reach 70% strength for lifting; 100% for driving.
  • Attach pile tip before lifting (no post-lift welding).
  • Use pile-specific helmets and cushioning (120–150mm compressed thickness).
  • Hammer cushions: 150–200mm hardwood or steel rope.

Pile Driving

  • Initial Penetration: Use low energy in soft layers.
  • Hard Strata: Drive continuously to minimize delays.
  • Stop Conditions: Abnormal resistance, pile damage, or excessive heave.
  • Blow Count Limits:
    • PC piles: ≤2000 total blows, ≤250 blows/last meter.
    • PHC piles: ≤2500 total blows, ≤300 blows/last meter.
  • Pre-Drilling (If Needed):
    • For hard layers/thick sand.
    • Drill diameter: 50–100mm smaller than pile.
    • Max depth: 12m; complete within same shift.

Splicing

  • Weld at 50–100cm above ground (2 layers, 3 passes).
  • Align sections (<2mm misalignment); weld symmetrically.
  • Cool naturally (≥5min for manual welding; ≥3min for CO₂).

Final Driving (Termination Criteria)

  • Primary Controls: Bearing layer + final penetration/blow count.
  • Penetration Standards:
    • Typically ≥20mm/10 blows (average of 3 readings).
    • For thin weathered rock: ≥15mm/10 blows.
  • Ensure load capacity overrides strict penetration rules.

Cutting & Inspection

  • Use pile cutters (no manual breaking).
  • Check: Elevation, length, position, and capacity.

Testing & Waiting Periods

  • High-Strain/Static Load Test Delays:
    • Sand: 7 days.
    • Silt: 10 days.
    • Clay: 15–25 days (saturated).
    • Water-sensitive rock: ≥25 days.
  • Test Quantities:
    • 1% static tests (min 3 piles); 20% integrity tests for risky sites.
    • 8% high-strain tests (min 10 piles) for others.

Post-Construction Protection

  • No excavation until pile work finishes (+15 days in clay/silt).
  • Deep excavations require staged plans and monitoring.
  • Limit soil pile height difference to 1m; avoid machinery contact.
  • Soft soil sites: Use manual excavation or ground improvement.
wedadmin

Recent Posts

10 Major Reasons and 9 Major Control Measures Affecting the Quality of Bored Piles

Bored cast-in-place piles have the advantages of low construction noise, and low vibration, pile length…

1 year ago

Common Quality Problems and Prevention Measures for Bored Pile Construction!

    Bored cast-in-place piles have the advantages of low construction noise, and low vibration,…

1 year ago

The Four Major Construction Techniques of Rotary Drilling Rigs Have Been Summarized for You!

The four major construction technologies are dry hole forming technology, slurry static pressure technology, casing…

1 year ago

Read the Soil Nail Wall Construction Technology in One Article!

Soil nail support is a new type of retaining structure developed in recent years for…

1 year ago

Summary of the Key Points of the Entire Construction Process of Bored Piles!

Pile Foundation Classification and Construction Principles 1. Classification According to Load-Bearing Piles ① Friction type…

1 year ago

Steel Sheet Pile Cofferdam Construction Method

Steel sheet pile cofferdams are suitable for basic projects such as sandy soil, gravel soil,…

1 year ago