Problems and Countermeasures in Deep Pile Construction
(1) Increase the length of the drill bit to increase the amount of ballast drilled per drill;
(2) The drill bit has a ventilation hole to increase the drilling speed;
(3) If it is not possible to enter the rock, try to use a friction rod to save the time of unlocking.
(1) The working site should be as flat and solid as possible to reduce the swing of the drilling rig;
(2) Frequently correct the leveling system to make the drill pipe work vertically;
(3) It is strictly prohibited to jack up the drilling rig when drilling under pressure;
(4) Add a centralizer to the drill pipe.
Countermeasures:
(1) Increase the height of the drilling tool;
(2) Add a centering ring to the drill pipe;
(3) Add a counterweight device to the upper part of the drill bit and use pressure at the bottom of the hole to make the drilling tool have a self-suspension effect when drilling.
Countermeasures:
(1) Due to the prolonged construction time of deep piles, if the wall protection effect is not good, the hole wall will become unstable, and high-quality mud should be prepared;
(2) The drill bit is equipped with a ventilation hole to reduce the impact and suction on the hole wall when lifting the drill.
Problems and Countermeasures in Large Pile Construction
(1) Select a reasonable drill bit (according to the formation conditions);
(2) Formulate a reasonable drilling plan. If the drilling rig has sufficient capacity and the formation is soft, it is best to drill the hole from the bottom to the bottom. If the footage efficiency is significantly reduced, graded drilling must be used, but two principles must be followed. One is steering. Drill until the bottom of the hole and then use a larger-diameter drill bit to enlarge the hole. Second, the diameter of the first drill should be selected reasonably. Generally, the drilled area should not be less than half of the total area.
Countermeasures:
(1) Drill pipe plus centralizer;
(2) When the lifting height and lifting capacity of the drilling rig are sufficient, increase the drill bit height as much as possible;
(3) Graded drilling can also prevent inclination. When drilling small diameters, the hole inclination is well controlled, and then when enlarging the hole, the drill bit will drill according to the original pilot hole trajectory.
(4) If you encounter a particularly inclined formation, try to use a long-length coring barrel to transition
Countermeasures:
(1) Strictly follow the correct usage method of drill pipe;
(2) It is best to use double pins for the drill pipe and drill bit and use a wire rope to secure the drill bit to the tray above the square head of the drill pipe. Even if the pin and the square head are broken, the drill bit will not fall into the hole;
(3) Put the drill bit on the ground and then open the door, or lift the drill bit off the ground and reverse it at high speed, so that the soil inlet between the two bottom plates opens and the ballast soil automatically leaks out.
Thanks
Bored cast-in-place piles have the advantages of low construction noise, and low vibration, pile length…
Bored cast-in-place piles have the advantages of low construction noise, and low vibration,…
The four major construction technologies are dry hole forming technology, slurry static pressure technology, casing…