Blog

Professional Guide to Dewatering Well Sealing: Best Practices for Construction Sites

Introduction

Proper sealing of dewatering wells is critical to ensure structural integrity and waterproofing in construction projects. This guide outlines the step-by-step process for effective dewatering well sealing, following the “inside-out” principle for optimal results.

Key Principles of Dewatering Well Sealing

  • “Inside-Out” Approach: Seal wells starting from the center before moving to peripheral ones.
  • Pre-Sealing Water Level Control: Maximize dewatering around the target well to minimize internal water pressure before sealing.
  • Final Well Caution: Exercise extra care when sealing the last remaining wells.

Step-by-Step Sealing Process

1. Dewatering System Design

  • Analyze engineering drawings and geological conditions to design an efficient dewatering system.
  • For localized deep areas (e.g., elevator pits, sumps), place wells centrally or nearby for maximum efficiency.
  • Position wells in areas with thinner waterproof slabs to simplify sealing and reduce costs.
  • Avoid interference with structural elements (piles, columns, shear walls, foundation beams).

2. Dewatering Well Construction

  • Install wells and initiate dewatering operations.

3. Excavation Precautions

  • Protect well openings with composite bamboo plywood to prevent soil ingress.
  • Reserve 300mm of soil around wells for manual excavation to avoid mechanical damage.

4. Waterproof Steel Sleeve Fabrication

  • Use Φ325×8 hot-rolled seamless steel pipes (height ≥ combined slab & footing thickness).
  • Fabricate waterproofing external rings (≥6mm steel, OD ≥525mm) and weld at sleeve mid-height.
  • Weld internal flange bolts and base reinforcement (4xФ20x150mm rebars).

5. Sleeve Installation

  • Fix the sleeve centrally over the well before footing concrete placement.

6. Waterproofing Membrane Application

  • Extend the membrane up to the sleeve’s external ring, sealed with waterproof mastic.

7. Slab Construction

  • Install additional rebar around sleeves per design specifications.

8. Well, Backfilling

  • Phase dewatering shutdown:
    1. Stop interior dewatering first.
    2. Seal interior wells.
    3. Stop exterior dewatering.
  • Backfill with graded gravel (base) and dry Portland cement (upper 2m).

9. Flange Sealing

  • Install 10mm rubber gaskets and tighten bolts crosswise for airtight compression.

10. Concrete Placement

  • Fill sleeve with high-grade dry concrete (one class above slab mix) and compact thoroughly.

11. Curing Protocol

  • Secondary compaction before the initial set.
  • Cure with plastic sheeting and felt (≥14 days) to minimize shrinkage.

Conclusion

Adhering to this methodical sealing process ensures long-term waterproofing performance and structural stability. Always align sequencing and timing with real-time site monitoring and design requirements.

wedadmin

Recent Posts

10 Major Reasons and 9 Major Control Measures Affecting the Quality of Bored Piles

Bored cast-in-place piles have the advantages of low construction noise, and low vibration, pile length…

1 year ago

Common Quality Problems and Prevention Measures for Bored Pile Construction!

    Bored cast-in-place piles have the advantages of low construction noise, and low vibration,…

1 year ago

The Four Major Construction Techniques of Rotary Drilling Rigs Have Been Summarized for You!

The four major construction technologies are dry hole forming technology, slurry static pressure technology, casing…

1 year ago

Read the Soil Nail Wall Construction Technology in One Article!

Soil nail support is a new type of retaining structure developed in recent years for…

1 year ago

Summary of the Key Points of the Entire Construction Process of Bored Piles!

Pile Foundation Classification and Construction Principles 1. Classification According to Load-Bearing Piles ① Friction type…

1 year ago

Steel Sheet Pile Cofferdam Construction Method

Steel sheet pile cofferdams are suitable for basic projects such as sandy soil, gravel soil,…

1 year ago