Blog

Pile Foundation Types: Construction Methods, Cost Analysis & Recommendations

Introduction

Pile foundations are essential for transferring structural loads to stable soil layers. This article compares three common foundation types—driven pipe piles, cast-in-situ piles, and CFG pile composite foundations—covering their definitions, construction processes, cost efficiency, and engineering advantages.

1. Pile Foundation Definitions

1.1 Driven Pipe Piles

Precast concrete pipes are sunk into the ground using static pressure equipment (jacketing or top-pressing) until reaching design depth or specified terminal pressure values.

1.2 Cast-in-Situ Piles

Formed by drilling, steel pipe soil displacement, or manual excavation to create boreholes. Reinforced with steel cages and filled with concrete. Subtypes include:

  • Driven cast-in-situ piles
  • Bored piles
  • Manual excavation piles

1.3 CFG Composite Foundation

CFG Piles (Cement-Fly Ash-Gravel):
High-strength columns are formed by cement, fly ash, gravel, and sand mixtures. Combined with inter-pile soil and cushion layers to create composite foundations.

2. Construction Processes

2.1 Driven Pipe Piles

Survey positioning → Pile rig setup → Position verification → Pile lifting/insertion → Verticality correction → Static pressing → Splicing → Continued pressing → Final driving → Quality inspection → Head cutting

2.2 Cast-in-Situ Piles

Site leveling → Hole positioning → Casing installation → Rig positioning → Drilling → Drill extraction → Primary cleaning → Inspection → Steel cage placement → Conduit installation → Secondary cleaning → Underwater concreting → Conduit removal → Pile completion

2.3 CFG Piles

Methods:

  • Long auger drilling
  • Drill-pump grouting
  • Vibratory tube sinking

Process:
Survey → Rig positioning → Drilling → Concrete mixing → Pumping & column formation

3. Foundation Types & Cost Analysis

3.1 Classification

  • Shallow Foundations (<5m depth): Isolated, strip, raft, box
  • Deep Foundations (≥5m depth): Pile, caisson, diaphragm walls

Common Shallow Foundations

Type Characteristics Applications
Isolated Square stepped design, cost-effective Light steel structures, equipment
Strip Linear, adaptable width Multi-story buildings
Raft Uniform settlement, high cost Basement projects
Box Rigid structure, expensive High-rises, underground stations

3.2 Economic Comparison

Key metrics:

  • Cost per kN bearing capacity
  • Total project expenditure

Case Study: Greenland Century City

  • PHC pipe piles showed 45.08% cost savings vs. bored piles
  • 13.63% more economical than CFG alternatives

4. Recommended Solution: PHC Pipe Piles

4.1 Advantages

Quality Assurance

  • Factory-produced (C80+ concrete)
  • Rigorous QC vs. cast-in-situ defects (necking, mud inclusion)

Design Flexibility

  • Capacity range: 600–3300 kN
  • Mixed-diameter configurations for load optimization

Economic Benefits

  • Lower material costs
  • 57-day total  (vs. 115 days for bored piles)

Construction Efficiency

  • Enables early excavation
  • Reduces dewatering risks

5. Schedule Comparison

Pile Type Test Pile Load Test Wait Testing Main Works Total
Bored Pile 7 days 28 days 20 days 60 days 115d
Driven Pipe 3 days 7 days 7 days 40 days 57d

Conclusion

PHC prestressed pipe piles deliver superior cost-performance ratios, quality control, and project timelines for most mid-to-high-rise developments. Their industrialized production and rapid installation make them the optimal choice for modern construction.