Blog

Soil Nailing Wall: Construction Process, Types, and Key Requirements

Soil nailing is a widely used reinforcement technique in excavation projects. It involves stabilizing slopes by installing steel-reinforced soil nails, followed by the application of a wire mesh and sprayed concrete layer to form a composite retaining structure.

Construction Process of Soil Nailing Wall

1. Slope Surface Preparation

  • Excavate soil in layers, with each layer depth matching the vertical spacing of soil nails.
  • The excavation level should be 200mm below the nail position.
  • Trim the slope surface, removing protruding soil and compacting loose areas to ensure a smooth shotcrete application.

2. Initial Shotcrete Layer

  • Apply concrete top-down, keeping the nozzle 0.8–1.5m from the surface.
  • Maintain a perpendicular spray angle with a minimum thickness of 40mm.
  • Use accelerators to enhance setting time and prevent slump.

3. Drilling & Cleaning for Soil Nails

  • Mark drill points according to design specifications.
  • Begin drilling slowly, increasing speed once a stable depth is reached.
  • Clean holes using high-pressure air or water to remove debris.

4. Soil Nail Installation

  • Cut reinforcement bars (+20cm longer than design length) with a 90° bend (20cm) at the outer end.
  • Install centralizers every 1–2m to ensure proper alignment.
  • Attach grout pipes (extending 0.5m from the hole bottom) and secure nails to the reinforcement mesh.

5. Grouting Process

  • Use pressure grouting, inserting the pipe 250–500mm from the hole base.
  • Seal the hole with a grout stopper and maintain pressure for 1–2 minutes after filling.
  • Slowly withdraw the pipe while ensuring the outlet remains submerged for complete air expulsion.

6. Reinforcing Mesh Installation

  • Install wire mesh layer by layer with:
    • ≥20mm cover thickness
    • ≥30d lap length (10d for single-side welding)
    • 0.5m extension beyond slope edges

7. Weep Hole Installation

  • Insert 400–600mm long, ≥40mm diameter weep holes (slightly downward) at 1.5–2m spacing.
  • Ensure pipes protrude from the shotcrete layer to drain accumulated water.

8. Final Shotcrete Application

  • Begin after mesh and nail inspections.
  • Spray perpendicularly in layers (first layer ≥40mm).
  • Allow each layer to set before applying the next.
  • Maintain 2h water curing post-setting to prevent cracking.

Key Technical Specifications

Types of Soil Nailing Walls

  1. Standard Soil Nailing Wall
  2. Prestressed Anchor Composite Wall
  3. Cement-Soil Pile Composite Wall
  4. Micro-Pile Composite Wall

Applicability & Requirements

  • Safety Levels: Suitable for Grade II & III excavation supports.
    • Standard walls: ≤12m depth (non-soft soil, above water table).
    • Prestressed anchor walls: ≤15m depth.
    • Cement-soil pile walls: ≤6m in soft clay.

Design & Construction Standards

Parameter Requirement
Slope Ratio ≤1:0.2
Nail Spacing 1–2m (H & V)
Drill Angle 5–20°
Hole Diameter 70–120mm
Reinforcement HRB400/500, Ø16–32mm
Grout Strength ≥20MPa
Shotcrete Thickness 80–100mm (≥C20)
Wire Mesh Ø6–10mm @150–250mm

Critical Construction Practices

✔ Follow “step-by-step excavation, immediate support” principles.
✔ Test nail pull-out resistance per layer.
✔ Complete nail & shotcrete within 24h (12h for soft clay).
✔ Allow 48h for grout setting before next excavation.
✔ Use 2-stage grouting:

  • 1st: Cement mortar (≥1.2x hole volume).
  • 2nd: Pure cement slurry (30–40% of 1st stage) @ 0.4–0.6MPa.
    ✔ Max aggregate size: 15mm.
    ✔ Minimum rebar cover: 25mm.