Blog

Construction Guide for Cement Deep Mixing Pile in Soft Soil Ground Improvement

1. Scope of Application

This guide applies to the construction of cement deep mixing piles (CDM) for soft soil ground improvement, ensuring stability and load-bearing capacity.


2. Pre-Construction Preparation

2.1 Site Preparation

  • Ensure “Three Supplies and One Leveling” (water, electricity, road access, and leveled ground).
  • Clear the site of debris, underground obstacles, and construction waste.
  • For low-lying areas, ponds, or marshes, drain water, remove silt, and backfill with compacted clay soil (avoid using mixed waste or garbage).

2.2 Technical & Survey Preparation

  • Review design documents and technical specifications.
  • Conduct a survey and stakeout with ≤ 20mm deviation tolerance.
  • Organize a technical briefing for the construction team.

2.3 Equipment Setup

  • Deploy cement mixing pile machines and conduct pre-operation checks.
  • Ensure smooth operation of drilling and grout pumping systems.

3. Technical Requirements

3.1 Trial Pile Testing

  • Perform test piles in representative areas to verify:
    • Soil conditions
    • Equipment suitability
    • Optimal parameters (drilling speed, rotation speed, pressure, current)
  • Confirm pile strength meets design requirements before full-scale construction.

3.2 Pile Specifications

  • Ensure pile diameter, length, and spacing comply with design standards.

4. Construction Process & Workflow

4.1 Construction Sequence

  1. Ground leveling
  2. Survey & marking
  3. Drilling machine positioning
  4. Drilling & grout injection
  5. Lifting & mixing
  6. Re-mixing (if required)
  7. Pile completion & machine relocation

4.2 Workflow Diagram

(Refer to Figure 1 for the detailed cement mixing pile construction process.)


5. Construction Requirements

5.1 Construction Methodology

5.1.1 Pre-Construction Preparation

  • Select cement & additives based on lab-tested mix designs.
  • Determine water-cement ratio, admixture dosage, and grout fluidity.
  • Mark pile locations with numbered stakes (≤ 50mm deviation tolerance).
  • Calibrate drilling depth using reference scales on the machine.

5.1.2 Pile Construction Process

  • Drilling:
    • Maintain vertical alignment (≤ 1.5% deviation).
    • Control sinking speed (0.5–0.6 m/min) with current ≤ 70A.
    • Avoid water injection unless necessary for hard soil layers.
  • Grout Mixing & Injection:
    • Prepare fresh cement slurry (sieve-filtered, no sedimentation).
    • Pump grout within 50m distance to prevent clogging.
  • Lifting & Mixing:
    • Maintain a consistent lifting speed for uniform mixing.
    • For interrupted operations, re-drill 0.5m below the stoppage point before resuming.
  • Final Quality Check:
    • Record grout volume, mixing time, and depth accuracy.

5.1.3 Quality Control Measures

  • Monitor grout density to prevent segregation.
  • Check pipe connections for leaks.
  • Clean equipment daily to avoid clogging.
  • For delays >3 hours, dismantle & clean pipelines before restarting.
  • Overlap adjacent piles by ≥50cm for continuity.

6. Workforce Organization

Role Quantity
Site Supervisor 1
Technical Engineer 1
Safety/QC/Survey Team 5–6
Machine Operators & Laborers 5–6

7. Material Requirements

  • Cement: Use fresh Portland cement (no clumping or moisture).
  • Water: Comply with JGJ63 Concrete Mixing Water Standards.

8. Equipment List

Equipment Model Qty
Pile Machine SJB-II 1
Grout Pump UB-3 1
Mixing Machine Vertical Type 1

9. Quality Control & Testing

9.1 Key Standards

  • Pile positioning error ≤50mm, verticality ≤ 1.5%.
  • Grout must be continuous (no sedimentation).
  • Base grouting: Hold for 30 sec at the pile bottom.
  • Overlap adjacent piles by ≥20cm (within 24 hours).

9.2 Testing Methods

  • 7-day strength check: Light penetration test or core sampling.
  • 28-day load test: For bearing capacity verification.

10. Safety & Environmental Compliance

10.1 Safety Measures

  • Hard hats & harnesses mandatory.
  • Electrical safety: Use grounded, insulated wiring.
  • Railway proximity work: Maintain 2m clearance from tracks.

10.2 Environmental Protection

  • Prevent cement spillage into water bodies.
  • Proper waste disposal (no on-site dumping).
  • Minimize noise & dust pollution.

Conclusion

This cement deep mixing pile (CDM) construction guide ensures high-quality soft soil stabilization while adhering to safety, efficiency, and environmental standards. Proper execution guarantees long-term structural integrity and compliance with international construction best practices.