With the development of high-rise buildings and underground spaces, excavation engineering—especially deep excavation projects—has become increasingly large-scale and complex, presenting numerous technical challenges. This field is also one of the most accident-prone areas in construction. Below, we outline the key construction points for excavation engineering.
01 Hazard Identification and Control in Excavation Engineering
Major Hazards
-
Excavation affecting adjacent structures or facilities requires special protection.
-
Continued use of structures beyond their designed service life.
-
Modifications to the original design, such as deepening, expanding, or changing usage conditions.
-
Nearby construction activities (e.g., pile driving, excavation, dewatering) affect excavation support safety.
-
Adjacent water sources.
General Hazards
-
Poor-quality materials, defects, structural damage, or other adverse conditions affecting safety.
-
Vibrations or shear forces from support structures or pile construction can cause soil liquefaction or seepage failure.
-
Severe leakage in waterproof curtains.
-
Major roads within the excavation influence zone or potential leaks from underground pipelines.
-
Reduced effectiveness of soil nails or shallow prestressed anchors during rainy seasons.
-
Sidewalls consisting of miscellaneous fill or special soil types.
-
Excessive heaving during excavation.
-
Vibrational loads on sidewalls.
-
Failure or progressive collapse of internal bracing.
-
Lateral impact loads on support structures.
-
Power outages, drainage system failures during typhoons or heavy rainfall.
-
Excessive deformation or ground cracks due to soil nail or anchor creep.
Hazard Control Measures
-
Pre-construction control: Develop risk mitigation measures in construction plans.
-
Construction process control: Strictly supervise and implement corrective actions.
Comprehensive Safety Management
-
Implement safety responsibility systems and establish management protocols.
-
Conduct safety training to enhance worker awareness.
-
Strengthen safety expertise among management personnel.
-
Apply preventive measures tailored to identified hazards.
02 Selection of Excavation Support Methods
Shallow Excavation (Depth <5m)
Common methods include:
-
Anchor and inclined strut supports: Suitable for large but shallow excavations.
-
Short pile and lagging wall supports: Used where partial slope cutting is insufficient.
-
Steel sheet pile supports: Ideal for low groundwater levels in cohesive or sandy soils.
Deep Excavation (Depth ≥5m or Complex Conditions)
Common methods include:
-
Soldier pile walls & diaphragm walls: For high-safety-grade excavations.
-
Cement-soil mixing walls: For medium-risk excavations.
-
Top-down arched walls: For low-risk excavations (not suitable for soft clay).
03 Key Excavation Techniques
Unsupported Excavation
-
Suitable for open areas with moderate depth.
-
Soft soils: Limit layer thickness to 2m and depth to 6–7m.
-
Hard soils: Layer thickness ≤5m (no depth limit).
Supported Excavation Methods
-
Bowl excavation: Central digging first, preserving slopes for temporary support.
-
Island excavation: Peripheral digging with central soil retained for stability.
Construction Guidelines
-
Follow “layered excavation, immediate cushioning” principles.
-
Combine excavation with slope reinforcement.
-
Use manual digging where machinery is impractical.
-
Pause excavation 200–300mm above the final grade for manual leveling.
-
Conduct pre-excavation monitoring for safety assurance.
04 Common Accidents and Mitigation
Excessive Displacement or Collapse
-
Displacement: Halt excavation, backfill if necessary.
-
Collapse: Install temporary steel sheet piles with shotcrete.
Base Heave or Soil Eruption
-
Heave: Backfill and reinforce the base soil.
-
Eruption: Install barrier piles and dewater.
Support Structure Defects
-
Leaks: Use grouting or polyurethane injection based on severity.
-
Void formation: Fill cavities via compaction grouting.
Adjacent Building Damage
-
Cracks/settlement: Halt work, consult experts, and reinforce soil via pressure grouting.
05 Excavation Monitoring
Monitoring Point Layout
-
Place horizontal/vertical displacement points along perimeter (3+ per side, ≤20m spacing).
Monitoring Techniques
-
Lateral soil movement: Measure via inclinometer tubes (accuracy ≥0.25mm/m).
-
Groundwater levels: Use piezometers (accuracy ≥10mm), distinguishing shallow/deep aquifers.
By adhering to these practices, excavation projects can mitigate risks and ensure structural and environmental safety.
