1. Tri-Axis Cement Soil Mixing Pile Construction Method and Key Technical Measures
1.1 Equipment Selection and Construction Method
This project utilizes the JB-160 tri-axis drilling machine for constructing Ф850@600 tri-axis cement soil mixing piles, with a total length of approximately 350,000 meters. The pile lengths are as follows:
-
K7+726–K7+755 (22m)
-
K7+755–K7+815 (22m)
-
K7+815–K7+965 (21m)
-
K7+965–K8+020 (10m)
Refer to the project’s enclosure drawings for detailed specifications.
Construction Sequence:
-
One tri-axis mixing pile machine will be deployed, starting from the south side of K7+726 and moving eastward.
-
Before construction, verify pile positions through measurement.
Construction Technique:
-
Ф850@600 tri-axis mixing piles adopt a method where the side shafts rotate forward for grout mixing while the central shaft rotates backward for air-jet mixing.
-
The “four-mixing, two-spraying” process (two up-down cycles with grout injection during descent) is applied.
-
After completion, conduct a waterproof curtain test before excavation to verify sealing effectiveness.
1.2 Construction Process Flow
1.3 Technical Requirements and Measures
1.3.1 Underground Obstruction Removal & Trench Excavation
-
Remove obstructions larger than 150mm (stones, concrete blocks).
-
Fill with plain soil; for river sections, construct cofferdams, dewater, dredge, and backfill.
-
Excavate a 1200mm wide × 1200-1500mm deep guide trench.
-
Ensure the construction platform is level (≤50mm deviation) and compacted before laying roadbed plates.
1.3.2 Surveying and Layout
-
Use a total station for control point measurement (four-round directional observation method).
-
Accurately mark pile centerlines and depths based on design drawings.
1.3.3 Construction Sequence
-
Skip-slot double-hole full re-mixing connection ensures overlapping quality.
1.3.4 Pile Machine Positioning
-
Adjust verticality (≤1/250) using a plumb bob.
-
Positioning deviation must be <20mm.
1.3.5 Mixing Speed and Grout Control
Key Parameters:
-
Cement: P.O 42.5, 20% cement ratio, water-cement ratio 1.5–2.0.
-
Lifting speed: ≤0.8m/min.
-
Cold joint treatment: Overlap with an extra pile or high-pressure jet grouting (HPJG) if intervals exceed 2 hours.
-
Deviation limits: Center offset ≤50mm, verticality ≤1/200.
Grout Preparation:
-
Mix on-site with a strict 2-hour usage limit.
-
Filter cement to prevent clogging; discard stagnant slurry after 2 hours.
Construction Monitoring:
-
Record下沉 sinking (sinking) and lifting speeds, depths, and grout volumes.
-
Ensure continuous operation to avoid pile breaks.
1.3.6 Joint Treatment
-
12–24h delay: Add 3 overlapping mixing piles externally.
-
>24h delay: Reinforce with 3 Ф800@500 HPJG piles.
1.4 Quality Inspection and Pile Testing
-
After 7 days, inspect pile integrity via excavation.
-
Core drilling (after 28 days): Test uniaxial compressive strength, continuity, and depth (≥2% of piles, min. 3 piles).
2. SMW Method Pile Construction and Key Technical Measures
2.1 Equipment and Construction Method
-
JB-160 tri-axis mixer constructs Ф850@600 (or Ф1000@750) SMW piles with embedded H700×300×13×24 (or H800×300×14×26) steel beams.
-
Arrangement:
-
Dense insertion at K7+559–K7+592.
-
Alternate insertion at K7+755–K7+965.
-
HPJG piles (Ф800@600) at corners/joints.
-
2.2 SMW Pile Construction Process
2.3 Construction Methodology
2.3.1 Site Preparation
-
Level and compact the ground to support 50-ton cranes and pile machines.
2.3.2 Surveying
-
Set control points using a total station; offset the enclosure pile centerlines by 10cm to account for deformation.
2.3.3 Guide Trench Construction
-
Dimensions: 1.0m (bottom) × 1.2m (top) × 0.6m (depth).
-
Align trenches precisely with pile axes (deviation ≤10mm).
2.3.4 Construction Sequence
-
Full-circle overlapping method ensures continuity.
2.3.5 Steel Beam Installation
-
H-beams are welded (E43XX electrodes), tested via UT, and coated with friction reducer (15% oxidized wax + additives).
-
Insert beams vertically (deviation ≤1/200) using a 50-ton crane.
2.3.6 Extraction of Beams
-
Post-construction: Extract beams after backfilling, using jacks and pure cement grout (W/C=1.15–1.18) to fill voids.
2.3.7 Quality Control
-
Core testing: ≥2% of piles (min. 3) for strength and integrity.
