1.1 Construction Process
The construction of the capping beam involves several critical steps to ensure structural integrity and compliance with design specifications.
1.2 Material Requirements
1.2.1 Concrete
-
Grade: C30 commercial ready-mix concrete is used for the capping beam.
1.2.2 Reinforcement Steel
-
Steel bars must meet design specifications in material and forming dimensions.
1.2.3 Formwork
-
Side Formwork: Prefabricated steel templates ensure smooth, clean, and deformation-free surfaces for easy demolding.
-
Reinforcement: Side formwork is secured using 10cm × 10cm wooden beams and 42mm diameter steel pipes with necessary fittings to ensure stability.
1.3 Key Construction Steps
1.3.1 Survey and Layout
-
A professional survey engineer marks the capping beam alignment using the exchange method.
-
After verification by on-site technicians, rebar binding proceeds.
-
Once formwork is erected, the capping beam elevation is checked and marked inside the template.
1.3.2 Earthwork Excavation
-
Excavation begins only after all supporting piles are completed and concrete reaches 75% of design strength.
-
Method: Mechanical excavation with manual assistance to prevent damage to pile reinforcement.
-
Soil is excavated 10cm above the capping beam base, followed by manual leveling to avoid soil disturbance.
-
The final excavation depth is 5cm below the beam base, and excavated soil is transported to designated areas.
1.3.3 Pile Head Removal
-
After exposing pile heads, manual jackhammers remove excess concrete and slurry up to the beam base level.
-
Strict elevation control prevents damage to the underlying pile structure.
-
Waste concrete is reused for backfilling, leaving a 30 cm-wide drainage trench beside the slope toe.
1.3.4 Base Leveling
-
After excavation, a 5 cm-thick M10 mortar layer levels the base.
-
Once hardened, template alignment lines are marked for precise formwork installation.
1.3.5 Reinforcement Works
1) General Requirements
-
All steel bars must have factory certifications and pass lab tests before use.
-
Surface must be free of oil, rust, or contaminants.
-
Straightening is done via winch, with ≤2% elongation for Grade I and ≤1% for Grade II steel.
-
Welding standards:
-
Double-sided weld ≥5d, single-sided ≥10d (d = bar diameter).
-
Electrodes: E43 for Grade I (stirrups), E50 for Grade II.
-
-
Spacing rule: No more than 50% of bars may have joints within a 35d (≥500mm) zone.
2) Rebar Processing
-
Cutting and bending follow design specs, with labeled storage to prevent mix-ups.
-
Tolerances:
-
Main bars: ±10mm in length.
-
Stirrups: ±5mm in dimensions.
-
Bent bars: ±20mm.
-
3) Installation & Binding
-
Clean and straighten pile-exposed bars before binding.
-
Key rules:
-
Stirrups must be perpendicular to the main bars, with overlaps staggered.
-
Binding wires secure all intersections (100% for single-leg stirrups).
-
Spacers maintain concrete cover thickness.
-
-
Allowable deviations:
-
Main bar spacing: ±10mm.
-
Layer spacing: ±10mm.
-
Stirrup spacing: ±10mm.
-
Cover thickness: ±5mm.
-
4) Embedded Parts & Openings
-
Install steel plates, monitoring points, etc., per design, with reinforced fixing to prevent displacement during concreting.
1.3.6 Formwork Engineering
1) Construction Method
-
Base: Plastic sheeting.
-
Sides: 30×15cm steel forms with cup-lock scaffolding support.
-
Bracing: Multi-layer steel pipe struts ensure dimensional accuracy.
2) Quality Control
-
Templates must maintain precise geometry and alignment.
-
Clean surfaces before concreting to enhance finish quality.
-
Monitor for deformation during pouring and adjust immediately.
3) End Formwork
-
Reinforced using longitudinal bars as tie rods or wedge anchors to resist concrete pressure.
4) Demolding
-
Forms are removed after concrete reaches sufficient strength (timing depends on ambient temperature).
-
Post-demolding, curing continues until compliance with standards.
1.3.7 Concrete Pouring
-
Pre-Pour Checks: Remove debris, pump out water, and inspect formwork.
-
Pour Length: Minimum 30m per batch to ensure continuity.
-
Compaction:
-
Use Ø35mm vibrators for dense zones.
-
Secondary vibration at pile-beam junctions prevents cracks.
-
Vibration time: ≥30 sec per point in a 50 cm-spaced grid.
-
-
Finishing:
-
Initial leveling with wood floats, final troweling after setting.
-
Workers use plywood walkways to avoid footprints.
-
-
Curing: Minimum 14 days of water curing (or insulation in cold weather).