Pile Foundation Construction Process (Static Pressure Piling)
Key Construction Steps:
-
Design Review & Preparation
-
Drawing review and approval
-
Pile numbering
-
Pile machine walking route planning
-
Pile foundation construction plan development
-
-
Pre-Construction Phase
-
Pile machine and personnel mobilization
-
Pipe piles, pile tips, and material submission for approval
-
Quality and technical briefings
-
Surveying and setting out (positioning and baseline verification)
-
Construction commencement application
-
-
Piling Execution
-
Test piling (to determine construction parameters)
-
Mass piling (after confirming parameters)
-
Pile integrity testing (high-strain dynamic testing, static load testing)
-
-
Post-Piling Activities
-
Excavation
-
Pile cutting (to the designed pile head elevation)
-
Post-excavation pile verification and deviation mapping
-
Low-strain integrity testing (reflection wave method)
-
If Class III defects are detected, additional piles are required
-
Final inspection report and foundation acceptance
-
Required Documentation
Pre-Construction & Material Approval
-
Material/Equipment Submission:
-
Construction materials, components, and equipment approval form
-
Quantity checklist
-
Product quality certification
-
Test Piling Documentation
-
Construction inspection application
-
Static pressure precast concrete/steel pile construction trial record
-
Pretensioned spun concrete pile quality inspection report
-
Precast concrete pile construction batch acceptance record
-
Concealed works quality acceptance record
Mass Piling Documentation
-
Construction inspection application
-
Static pressure precast concrete/steel pile construction record
-
Pile quality inspection report
-
Batch acceptance record
-
Concealed works quality acceptance record
Post-Excavation Documentation
-
Construction inspection application
-
Pile recheck and quality inspection report
-
Pile deviation map
Basement Retaining Wall Construction Process
Deep Excavation Support (Bored Pile Wall)
-
Construction of retaining piles
-
Capping beam construction
-
Excavation
-
Anchor cable installation
-
Waist beam construction
-
Anchor cable tension testing
-
Anchor head & fixture installation
Shallow Excavation Support (Mixing Pile Method)
-
Mixing pile construction → Excavation → Anchor installation → Tension testing → Waist beam construction
Slope Support Method
-
Excavation → Slope formation → Soil nailing → Reinforced mesh installation → Shotcreting
Anchor Cable Construction Process
-
Drilling
-
Anchor cable/bar insertion
-
Grouting (cement paste)
-
Waist beam installation
-
Tension testing
-
Anchor head & fixture setup
Required Documentation
-
Anchor/soil nail drilling record
-
Grouting construction record
-
Tension test record
-
Concealed works acceptance record
-
Anchor/soil nail wall batch acceptance record
Bored Pile Construction Process
-
Slurry wall quality inspection (during drilling)
-
Drilling record
-
Pile concealment acceptance
-
Rebar cage installation acceptance
-
Underwater concrete pouring record
-
Concrete concealment acceptance
-
Post-construction data compilation
Testing Requirements
-
Concrete test samples (during pouring)
-
Rebar welding test samples (during cage fabrication)
-
Rebar material testing
Mixing Pile Construction
-
Process: Cement mixing → Machine positioning → Drilling (with water/cement injection) → Pile formation → Light dynamic penetration test (after 3 days)
-
Testing: Cement, cement-soil samples, rebar
Quality Control & Field Testing
-
Anchor/Tieback Testing
-
Tension tests at 28 days to verify design strength
-
-
Bored Pile Core Sampling
-
Core extraction at 28 days to assess concrete strength and integrity
-
-
Mixing Pile Testing
-
Light dynamic penetration test (3 days post-construction)
-

