1. Dealing with Deviated Drilling Holes
Quality Problems and Phenomena
-
Non-vertical holes after completion with deviation exceeding the specified L/100
-
Difficulty in inserting reinforcement cages
Causes
-
Unlevel drilling rig or an uncompacted construction site causing uneven settlement
-
Unstable underwater drilling platform foundation
-
Bent drill pipes or loose connections are causing excessive drill bit movement
-
Obstacles near existing structures are pushing drill bits sideways
-
Uneven soil hardness or encountering boulders
Preventive Measures
-
Level and compact the site before rig positioning; regularly check levelness during drilling
-
Align the pulley groove, the drill pipe chuck, and the centerline vertically
-
Conduct pre-construction surveys near existing structures; use impact drilling if obstacles are found
-
Regularly inspect and replace bent drill pipes
-
For impact drilling, use appropriate stroke and consider two-stage hole forming
Treatment Methods
-
Use impact drilling for boulders
-
For excessive deviation, backfill with clay and redrill after compaction
2. Handling Hole Shrinkage During Drilling
Quality Problems
-
Difficulty in lowering the hole detector due to diameter reduction
Causes
-
Weak soil layers compress inward
-
Water-expanding plastic soil layers
-
Worn drill bits are not repaired timely manner
Prevention
-
Frequently ream holes when encountering weak/plastic soils
-
Regularly inspect and repair drill bits
Treatment
-
Ream hole repeatedly until the design diameter is achieved
3. Managing Hole Collapse During Drilling
Quality Problems
-
Wall collapse during/after drilling
Causes
-
Inadequate mud density or leaking casing
-
Low mud pressure on walls
-
Fast advancement in sandy layers
-
Long drilling interruptions
-
Equipment vibration near the site
Prevention
-
Avoid heavy equipment near the site
-
Properly install and seal casings
-
Adjust mud properties according to geology
-
Maintain continuous operation
-
Handle reinforcement cages carefully
Treatment
-
For severe cases, redrill after proper backfilling
4. Addressing Stuck Drill Bits
Quality Problems
-
Immobilized drill bit during operation
Causes
-
Irregular hole shapes
-
Improper bit lowering
-
Falling debris
-
Over-sized repaired bits
Prevention
-
Use proper drilling techniques
-
Ensure the bit size matches the hole diameter
-
Control impact energy
Treatment
-
Try gentle maneuvering
-
Use jacks or pulley systems for extraction
-
Consider controlled blasting in hard strata
5. Preventing Casing Bottom Collapse
Quality Problems
-
Casing wall collapse and rig tilting
Causes
-
Improper clay backfilling
-
Inadequate geological data
-
Undersized casing
-
Water infiltration
Prevention
-
Backfill with ≥50cm of clay around the casing
-
Extend casing through weak layers
-
Use properly sized casings
-
Seal casing properly
Treatment
-
For underwater cases, sink casing deeper
-
For bottom collapse, reposition and reinforce the casing
6. Preventing Reinforcement Cage Deformation
Quality Problems
-
Excessive twisting/bending during handling
Causes
-
Lack of temporary supports
-
Improper lifting points
-
Insufficient stiffener rings
Prevention
-
Add stiffeners every 2-2.5m
-
Use proper lifting techniques
-
Install temporary supports for long cages
Treatment
-
Severely deformed cages must be remade
7. Securing Positioned Reinforcement Cages
Quality Problems
-
Cage sinking or displacement
Causes
-
Improper fixation
-
Measurement errors
-
Reference point movement
Prevention
-
Secure cages to the casing with wooden blocks
-
Compact backfill around casing
-
Verify measurements carefully
Treatment
-
Use cranes to reposition before concreting
8. Preventing Reinforcement Cage Flotation
Quality Problems
-
Upward cage movement during concreting
Causes
-
Fast concrete placement near the cage bottom
-
Hanging on a rising pipe
Prevention
-
Slow placement near the cage
-
Center pipes properly
-
Anti-snag measures
Treatment
-
Apply downward pressure if flotation begins
9. Avoiding Broken Piles in Underwater Concreting
Quality Problems
-
Mud inclusion or discontinuous piles
Causes
-
Pipe blockages
-
Improper pipe positioning
-
Over-extraction
-
Leaking pipes
Prevention
-
Test pipes before use
-
Maintain proper embedment depth (2-4m)
-
Control concrete workability
-
Have backup equipment
Treatment
-
Various unblocking techniques for clogged pipes
10. Ensuring Pile Head Quality
Quality Problems
-
Premature cracking or irregular surfaces
Causes
-
Early demolition
-
Inadequate overpour
-
Mud contamination
Prevention
-
Allow proper curing (≥70% strength)
-
Overpour by ≥80cm
-
Demolish carefully
-
Prohibit blasting methods
Treatment
-
Continue demolition until sound concrete is reached
11. Correcting Pile Center Deviation
Quality Problems
-
Misaligned pile positions
Causes
-
Positioning errors
-
Improper casing
-
Cage misplacement
Prevention
-
Careful measurement verification
-
Proper casing installation
-
Accurate cage positioning
12. Ensuring Quality in Dug Pile Concreting
Quality Problems
-
Segregation or low strength
Causes
-
Poor materials/mixing
-
Improper placement
-
Water presence
-
Nearby dewatering
Prevention
-
Use proper mixes
-
Employ tremie pipes
-
Control water conditions
-
Coordinate nearby work
Treatment
-
Additional piles if the strength is inadequate
13. Preventing Waterlogged Foundations
Quality Problems
-
Softened base from water
Causes
-
Rainfall
-
High water table
-
Insufficient dewatering
Prevention
-
Time excavation carefully
-
Perimeter drainage
-
Adequate pumping
-
Cutoff trenches
Treatment
-
Replace softened material with granular fill
14. Stabilizing Foundations on Uneven Strata
Quality Problems
-
Sliding or tilting foundations
Causes
-
Uneven bearing capacity
-
Hillside locations
-
Synclinal strata
Prevention
-
Create stepped foundations
-
Ground improvement
-
Full excavation
-
Rock anchoring
Treatment
-
Grouting to strengthen weak zones
15. Mass Concrete Quality in Pile Caps
Quality Problems
-
Surface or through cracks
Causes
-
Ground movement
-
Thermal stress
-
Plastic shrinkage
Prevention
-
Uniform foundation preparation
-
Thermal control measures
-
Proper curing
-
Construction joints, if needed
Treatment
-
Crack injection or reinforcement
16. Quality Control for Pier Concreting
Quality Problems
-
Honeycombing, poor finish
Causes
-
Improper materials
-
Segregation
-
Poor vibration
Prevention
-
Avoid slag cement
-
Control slump
-
Use tremie pipes
-
Proper vibration
Treatment
-
Patch minor defects
17. Preventing Horizontal Cracks at Pier Tops
Quality Problems
-
Cracking near the top
Causes
-
Low pressure
-
Over-vibration
Prevention
-
Secondary vibration
-
Remove top ties
-
Apply surcharge
Treatment
-
Epoxy injection or reconstruction
18. Accurate Bearing Plate Installation
Quality Problems
-
Misaligned plates
Causes
-
Measurement errors
-
Poor fixation
-
Voids underneath
Prevention
-
Careful positioning
-
Secure welding
-
Center hole technique
Treatment
-
Reinstallation with proper anchoring
19. Addressing Local Collapse in Slipforming
Quality Problems
-
Edge failures
Causes
-
Improper segmentation
-
Fast lifting
-
Uneven jacks
-
Poor vibration
Prevention
-
Proper segmentation
-
Controlled lifting
-
Jack synchronization
-
Thorough vibration
Treatment
-
Patching or reconstruction
20. Correcting Template Deviation in Slipforming
Quality Problems
-
Twisting/misalignment
Causes
-
Uneven jack speed
-
Uneven loading
-
Improper concreting
-
Wind effects
Prevention
-
Synchronized jacks
-
Balanced loads
-
Proper placement
Treatment
-
Adjust jack speeds differentially
-
Correct tilt before twist