Blog

Underground Diaphragm Wall Construction: Techniques and Best Practices

Introduction

Underground diaphragm walls are a common construction method in municipal engineering, widely used in deep foundation pits for urban projects. After completion, they form a continuous reinforced concrete wall underground, serving multiple purposes such as water cutoff, seepage prevention, load-bearing, and retaining structures.

1. Construction Process of Underground Diaphragm Walls

1.1 Construction Preparation

Construction Roads

  • Bearing Capacity Requirements: The foundation must support heavy equipment such as excavators, cranes, and concrete transporters, with a required bearing capacity of at least 100 kN/m².

  • Road Specifications:

    • Width: 9–12 m (to accommodate 200–320T crawler cranes with a walking width of 7–9 m).

    • Thickness: 250 mm reinforced concrete (typically single-layer bidirectional reinforcement).

Guide Walls

Functions:

  • Serves as a measurement reference and trenching guide.

  • Stores slurry to stabilize trench walls.

  • Supports the upper soil to prevent collapse.

  • Bears construction loads (e.g., excavation machinery, rebar cage installation).

Construction Requirements:

  • Minimum thickness: 200 mm.

  • Embedment depth: ≥1.5 m (must penetrate non-fill layers by at least 200 mm).

  • Common structural forms: Inverted “L” (for stable soil) or “[“-shaped (for weaker soil).

  • For soft or loose soil, use soil replacement, trench wall reinforcement (e.g., jet grouting, TRD method), or deep guide walls.

1.2 Slurry Preparation

Functions:

  • Wall stabilization.

  • Cuttings removal.

  • Cooling and lubrication of equipment.

Quality Control:

  • Slurry mix design should account for geological and groundwater conditions.

  • Performance indicators for fresh and recycled slurry must meet standards.

  • Slurry storage capacity: ≥2× daily maximum trenching volume.

  • The slurry circulation system includes mixers, storage tanks, pumps, pipelines, and desanders.

1.3 Trenching

Equipment Types:

  • Grab Machines: Suitable for soils with SPT-N <40 (clay, sand, gravel).

    • Depth: Typically 60–80 m (sufficient for building projects).

    • Efficiency: 8–10 hrs for 35 m walls; ~20 hrs for 60 m walls.

  • Impact Machines: Used in hard rock or boulder layers (low efficiency).

  • Hydraulic Cutters (Hydrofraise):

    • Advantages: High precision (verticality 1‰–2‰), deep excavation (up to 150 m), and adaptability.

    • Limitations: Expensive, sensitive to obstructions (e.g., rebar, boulders).

Trench Division:

  • Segment length: 4–6 m (must exceed grab machine’s horizontal reach of 2.8 m).

  • For SPT-N >50 or rock UCS >3 MPa, use combined grab-impact or grab-cutter methods.

1.4 Joint Systems

Types:

  • Flexible Joints: Pipe joints, hinge joints, cutter joints.

  • Rigid Joints: H-pile joints, cross-steel plate joints, V-plate joints.

Comparison:

Joint Type Pros Cons
Pipe Joint Simple, cost-effective Weak shear resistance, leakage risk
H-Pile Joint High stiffness, good waterproofing Complex installation
Cross-Plate Joint Excellent seepage control High steel consumption, expensive
Hydrofraise Joint No pre-excavation needed, high quality Requires strict sequencing

1.5 Rebar Cage Construction

Fabrication:

  • Use welding or mechanical couplers (lap joints must stagger by 50%).

  • HRB400 bars (or HRB335 bars ≥25 mm) require mechanical connections.

  • Install lateral supports (2–3 rows) and vertical trusses (4–5 m spacing).

Lifting:

  • Typical weight: 50T (60 m wall)70T (with H-pile).

  • Use 250–350T main crane + 100T auxiliary crane.

  • Avoid segmented lifting to ensure stability.

1.6 Concrete Pouring

Requirements:

  • Slump180–220 mm (underwater concrete).

  • Aggregate size: ≤1/3 of rebar spacing or 1/6–1/8 of pipe diameter.

  • Placement:

    • Dual-pipe method (spacing ≤3 m).

    • Initial embedment depth: ≥0.8 m; maintain 2–6 m during pouring.

Quality Checks:

  • Test slump (3+ times per segment) and compressive strength (1 sample/100 m³).

  • Conduct ultrasonic integrity tests (20% sampling) or core drilling.

1.7 Post-Grouting

Specifications:

  • Use P.O.42.5 cement (water-cement ratio: 0.5–0.6).

  • Grout pipes (≥3 per segment) should extend 200–500 mm below wall base.

  • Start grouting after concrete reaches 70% strength.

  • Termination criteria:

    • Grout volume meets design, OR

    • Pressure >2 MPa for 3 mins + 80% design volume.


2. Structural Measures for “Integrated Wall” Systems

2.1 Wall Top Lowering

  • Purpose:

    • Accommodate concrete overflow (300–500 mm above design).

    • Avoid conflicts with utility pipes.

    • Merge capping beams with wales to reduce costs.

2.2 Settlement Control

  • Solutions:

    • Install edge piles near walls.

    • Use low-rebar or plain concrete in non-load-bearing sections.

    • Enhance connections with structural beams/slabs.

2.3 Leakage Prevention

  • Techniques:

    • Rigid joints (e.g., I-shaped) + outer RJP/MJS jet grouting.

    • Internal brick/RC lining with drainage channels.

    • Waterstops at wall-slab joints.


3. Safety & Environmental Compliance

3.1 Safety Measures

  • Equipment: Operated by certified personnel.

  • Trench Access: Restricted without proper safeguards.

  • Crane Zones: Marked exclusion areas.

3.2 Environmental Protection

  • Sludge Management:

    • Centralized storage.

    • No direct discharge into waterways.

    • Use sealed trucks for transport.

  • Site Monitoring: Pre-construction surveys + real-time building/pipeline checks.


Conclusion

Underground diaphragm walls are a versatile solution for urban deep excavations. Proper construction techniques, joint selection, and waterproofing ensure structural integrity and longevity, especially in “two-wall-in-one” applications. Adherence to safety and environmental protocols further guarantees project success.