1. Construction Preparation
① Inspection and Classification
-
Transport new and used steel sheet piles to the site.
-
Conduct detailed inspections, measurements, and classification, labeling each pile accordingly.
② Repair and Modification
-
Straighten bent, damaged, or improperly locked sheet piles using cold bending, hot forging, welding, or cutting.
-
For insufficient lengths, weld additional sections of the same type—first butt welding, then reinforcing with steel plates.
2. Installation of Steel Sheet Pile Cofferdam
① Guide Frame Setup
-
Precisely measure and drive two sheet piles, then weld steel brackets.
-
Place two additional sheet piles on the brackets to form a stable guide frame (removed and reinstalled after completion).
② Pile Driving
Equipment:
-
10-ton floating crane
-
60T hydraulic vibratory pile hammer
-
Transport barge (modified from three standard barges)
-
40T crawler crane
Driving Method:
-
Install three sides of the rectangular cofferdam first, then the final side after alignment.
-
Advantages: Faster installation, minimal alignment errors, and easier closure.
Driving Sequence:
-
Start upstream, then proceed downstream for closure.
Verticality Control:
-
Two workers monitor alignment using plumb lines from 50–100 meters away.
3. Cofferdam Sealing
① Dredging
-
After closure, remove sediment using divers and high-pressure water jets.
-
A slurry pump extracts loosened mud from the basin.
② Rock Filling and Concrete Sealing
-
After reaching design elevation, fill with 50 cm of crushed stone (max. 20 cm diameter).
-
Pour a 1.5 m thick underwater C25 concrete seal in one continuous operation using tremie pipes (3.0 m effective radius).
4. Installation of Internal Bracing
① Setup After Sealing
-
Begin dewatering and install wales and bracing once concrete reaches 50% strength.
② Key Principles:
-
“Brace first, dewater later”—install supports layer by layer during dewatering.
-
First, dewatering is critical; ensure sufficient pumps for rapid water removal.
-
Reinforce corners with steel sections due to complex stress distribution.
③ Monitoring
-
Focus on deformations in wales, bracing, and sheet piles.
-
If excessive movement occurs, halt dewatering, refill the cofferdam, and reinforce before resuming.
Case Study: Main Pier Foundation Construction
Project Overview:
-
Design: 16 × φ250 cm piles, 52 m deep.
-
Challenge: Steep riverbed with 12 m water depth variation.
Innovative Solutions:
-
Modified double-wall steel cofferdam with rectangular, asymmetrical high-low cutting edges.
-
Installed using a guide frame barge.
-
Step-like concrete pouring with partition plates to reduce material usage.
Construction Steps:
-
Fabricate a cofferdam on-site.
-
Install using guide barges.
-
Stabilize and set steel casings.
-
Form a drilling platform for pile construction.
-
After pile testing, dewater, trim piles, and build the cap.
