1. Design Basis
| No. | Name | Code |
|---|---|---|
| 1 | Engineering Survey Code | GB50026-2007 |
| 2 | Code for Acceptance of Construction Quality of Building Foundation | GB50202-2018 |
| 3 | Unified Standard for Construction Quality Acceptance of Building Engineering | GB50300-2013 |
| 4 | Code for Design of Building Foundation | GB50007-2011 |
| 5 | Technical Code for Building Pile Foundation | JGJ94-2008 |
| 6 | Technical Code for Testing of Building Foundation Piles | JGJ106-2014 |
| 7 | Prestressed Concrete Pipe Pile | 10G409 |
| 8 | Construction Organization Design of This Project | – |
| 9 | Design Drawings of This Project | – |
2. Project Overview
| Item | Content |
|---|---|
| Project Name | – |
| Project Address | – |
| Construction Unit | – |
| Design Unit | – |
| General Contractor | – |
| Supervision Unit | – |
Construction Scope:
This project uses prefabricated PHC prestressed concrete pipe piles with cross-shaped steel plate pile tips. The installation method employs static pressure. Pile specifications include:
-
Diameter: 400mm
-
Wall thickness: 95mm
-
Type: AB
-
Concrete grade: C80
-
Total quantity: 358 piles
Elevation Reference:
±0.000 corresponds to Huanghai elevation 7.350m
Pile Specifications:
-
ZH-1:
-
Design pile top elevation: -2.050m
-
Effective length: ~38m
-
Single pile vertical bearing capacity: 800KN
-
Bearing layer: completely weathered coarse-gravel sand
-
Required penetration into bearing layer: ≥0.8m
-
-
ZH-2/ZH-3:
-
Design pile top elevation: -0.450m to -0.520m (ZH-2), -0.900m (ZH-3)
-
Effective length: 34m
-
Single pile vertical bearing capacity: 550KN
-
Bearing layer: silty clay
-
Required penetration into bearing layer: ≥0.8m
-
3. Construction Preparation
3.1 Site Preparation
-
Remove overhead and underground obstacles affecting pile driving
-
Level the construction site with a ≤2% slope and ensure proper drainage
-
Reinforce soft ground areas to support pile driving equipment
-
Establish control points for pile axes and benchmarks outside construction impact zones
-
Complete workforce mobilization and conduct technical safety briefings
3.2 Pre-construction Testing
-
Conduct trial tests on 6 piles to verify:
-
Single pile bearing capacity
-
Suitability of selected equipment and methods
-
Design parameters and treatment effects
-
4. Static Pressure PHC Pile Construction
4.1 Construction Process Flow
Measurement & Positioning → Pile Material Inspection → Machine Positioning → Pile Driving (with splicing) → Pile Feeding → Testing
4.2 Key Construction Requirements
4.2.1 Pile Delivery & Storage
-
The manufacturer must provide quality certificates matching batch numbers
-
Maximum stacking: 3 layers with proper wooden supports
-
The storage location should minimize transportation distance
-
Implement careful handling to prevent damage
4.2.2 Positioning & Verticality Control
-
Use the grid method for accurate center point marking (±20mm tolerance)
-
Employ two theodolites at 90° for verticality monitoring (≤0.5% deviation)
-
Strictly control the first section’s verticality (≤0.3%) as guidance for subsequent sections
4.2.3 Driving Process
-
Maintain driving speed ≤1m/min
-
Continuous operation without unnecessary stops
-
Prohibit equipment adjustment after the pile enters a hard soil layer
-
Complete real-time recording with supervisor verification
4.2.4 Pile Splicing
-
Welding requirements:
-
Surface cleaning to bare metal
-
Maximum joint misalignment: 2mm
-
Natural cooling time: ≥8 minutes
-
Weld inspection sampling: ≥3 joints per project
-
5. Quality Inspection Methods
5.1 Low Strain Testing
-
Random sampling: ≥20% of total piles (minimum 10 piles)
-
Concrete strength requirement: ≥70% design strength (minimum 15MPa)
-
Determine the effective detection range through field tests
5.2 Static Load Testing
-
Method: Slow, maintained load approach
-
Quantity: 6 test piles
-
Minimum rest period:
-
28 days after installation
-
14 days without nearby pile driving
-
-
Loading procedure:
-
Incremental loading (10% of estimated ultimate capacity)
-
ZH-1 ultimate load: 2200KN
-
ZH-2/ZH-3 ultimate load: 1100KN
-
Termination Criteria:
-
Settlement exceeds 5× the previous level
-
Reaching design load with stable settlement
-
Settlement exceeds 2× the previous level without stabilization after 24h
6. Safety Measures
-
Operator certification requirement
-
Equipment angle limits:
-
Forward tilt ≤5°
-
Backward tilt ≤18°
-
-
Mandatory safety gear (hard hats, etc.)
-
Site requirements:
-
≤2% slope
-
No underground obstructions
-
Clear warning signs
-
-
Electrical safety:
-
Overhead cables
-
Minimum 6m clearance from high-voltage lines
-
-
Weather restrictions:
-
Prohibition during heavy rain, fog, or >6级 winds
-
7. Quality Assurance System
7.1 Three-Level Management
-
Team self-inspection
-
Quality department joint inspection
-
Project manager periodic sampling
7.2 Key Procedures
-
Strict technical disclosure system
-
Three-check system (self/mutual/special inspection)
-
Comprehensive documentation
-
Regular equipment calibration
7.3 Process Control
-
Material traceability
-
Construction parameter monitoring
-
Non-conformance handling protocol
-
Continuous improvement mechanisms
This technical specification provides complete guidance for PHC pile construction while optimizing for search engine visibility through:
-
Clear section organization
-
Technical keyword integration
-
Comprehensive coverage of construction processes
-
Standard-compliant terminology
-
Detailed quality control measures